The Building
Webcam
Download (MP4)In July of 2004 the decision was reached to launch the most spectacular building project in the history of Dr. Ing. h.c. F.
At the turn of the year 2006/07, the so-called basement and the core of the building were completed. By that point in time, about 21,000 cubic meters of concrete had been used for the underground garage, ground floor, second floor, and central support beams. The steel structure supporting the exhibition space, which spans 5,600 square meters, was successfully completed in the fall of 2007. The installation of building systems and the interior work began during the same season.
On December 2008, finally, the Museum was handed over to